The yard restoration scope should name who does each repair and who checks it with the owner. At the winter scope meeting for a summer 2027 fiberglass pool, walk the proposed construction route together. Mark the fence, lawn, paving and plants the owner expects to keep, then use those notes to define what each party will put back.
Mark the construction route and the permanent service path
Cary’s residential pool permit packet asks for a plot plan showing the proposed pool, decking or paving, above-ground mechanical and utility equipment, and screening. It also asks for a pool barrier fence sketch. [Town of Cary pool permit packet](https://www.carync.gov/home/showpublisheddocument/1615/638948304888400000)
Use a working copy of the project survey or plot plan to draw the temporary crew route and outline the area covered by restoration. Mark the permanent path from the gate to the equipment pad on the same copy. Put the agreed gate opening and any landscaping limits in the scope so the fence and landscape crews know how much room to leave for service.
Assign the fence, lawn and utility work by name
Say the crew needs to remove a side fence panel and cross the lawn to reach the backyard. An example scope could put the fence subcontractor in charge of removing and reinstalling the panel, the landscape subcontractor in charge of repairing ruts and replacing turf within the marked strip, and the builder’s superintendent in charge of keeping the route open until the last subcontractor using it has finished. Assign the superintendent to check the fence, posts and lawn against photos from the initial walk. If the owner is arranging the lawn repair separately, record that assignment and when the builder expects to release the route.
NC 811 identifies the water service from the meter to the residence as a private line and directs customers to a private line locator. [NC 811 Private Lines](https://www.nc811.org/education/private-lines.html)
If the planned route crosses that service, name who will book the private locator before any digging in the crossing area. Write down who will review the markings with the crew and update the route if the findings call for a change.
Check local crew availability before signing
Ask the fence and landscape crews about lead times and availability for the planned sequence, including who can return after the last construction crew leaves. On a coastal lot, ask whether sand or existing vegetation changes what the landscape crew would include. On an inland lot, ask the same about slopes or established turf. Write the answer for the actual property into the scope and name who will rebook the crews if the sequence changes.
Walk both routes at owner handoff
Walk the former construction route with the owner and take handoff photos from the same spots as the initial photos. Check the fence and lawn against the agreed repair limits. Then walk from the restored gate to the equipment pad and confirm that the fence and landscaping leave the agreed service path clear. Give the owner a written list of any unfinished work, with a named person and follow-up date for each item. Start the winter scope meeting with the lot plan and leave with those responsibilities written beside the work they cover.