Compare two staging locations on the Pender County lot
On a Pender County pool job, the shortest delivery approach might put the unloading area beside a vegetated strip whose status is uncertain. Draw that option and a second one using an existing paved area, if available. Use the same dated parcel drawing for both and show the proposed permanent equipment pad in the same place on each. Mark the approximate edge of the vegetated strip and flag it for verification. Pender County is covered by the Coastal Area Management Act (CAMA), and NC DEQ advises checking whether a project falls within an Area of Environmental Concern because that can affect permitting.
Show the full temporary footprint and dates of use
For each option, shade the delivery approach, equipment standing area, shell set-down location and any space needed for materials or excavated soil. Label the expected dates or date ranges for each use and mark any estimates as tentative. The paved option might move the unloading point away from the strip while leaving a soil pile beside it for several days. Showing both uses lets the reviewer see which activity comes closest to the strip and how long it would occupy that space.
Ask about the strip before issuing the delivery drawing
Use NC DEQ’s Local Permit Officer listing or field representative locator to find a contact for the parcel. Send both sketches and ask who should review them, how to verify and depict the strip, and whether any part of either temporary footprint affects the permit review. Record the response and any requested changes on the revised drawing. Give the delivery coordinator and site lead the same dated version before they commit to a staging location.