Confirm what Cary needs to see before and after the shell set
Before booking fiberglass shell delivery and the set crew, ask Cary’s Inspections & Permits staff what must be inspected or cleared before the shell is set and what must remain visible afterward. Have the permit drawings open for that conversation. Cary’s residential pool submittal calls for a plot plan showing the pool, decking or paving, above-ground mechanical and utility equipment, and equipment screening, along with a sketch of the barrier fence. Use those drawings to point to the areas where later work could cover something staff need to see.
Put Cary’s permit-specific answers in the schedule
Ask which inspection requests apply to this permit, what needs to be ready or visible for each visit, and which work must wait for clearance. Walk through the shell set, deck work and barrier installation with staff. For each hold Cary confirms, record the work being held, the inspection or clearance Cary identifies, who will request it and where the result will be recorded. Share the entries with the superintendent before firming up crew dates.
Keep an early deck slot tentative until the hold is cleared
Suppose the deck crew offers an earlier pour date and Cary has told you that the area beside the shell must stay exposed for a visit on this permit. A sample schedule entry would read Work held — pour the deck beside the shell. Clearance — Cary’s permit-specific visit while the area is exposed, using the inspection name Cary provides. Requester — superintendent. Recorded result — pending, with the date and outcome to be entered after the visit. If Cary calls for a correction, have the superintendent confirm whether another visit is needed before releasing the pour. If the pour shifts, update any fence work that depends on it before giving the owner a revised completion estimate.